To create a room schedule in current versions of Revit: choose View > Schedules > Schedule/Quantities, select the Rooms category, add the fields you need, and then refine sorting, grouping, filters and formatting in Schedule Properties.
Technical check: 2 September 2026. Revit schedules are model views: changes to editable values in a room schedule can update the corresponding room data.
Why is creating a room schedule in Revit Important?
Creating a room schedule in Revit is a crucial step in organising and managing information about the various spaces in your project.
Here’s a step-by-step guide to help you create a room schedule:
Step 1: Save Your Work:
- After completing your design in Revit, save your work to ensure you don’t lose any changes.
Step 2: Navigate to the Project Browser:
- Locate and click on the Project Browser at the bottom left of the page.
Step 3: Access ‘Schedule/Quantities (all)’:
- Use View > Schedules > Schedule/Quantities to create a new schedule
Step 4: Choose Schedule Type:
- In the ‘New Schedule’ dialog, ensure you are selecting the appropriate schedule type. For rooms, choose ‘Architecture.’ Under ‘Category’, scroll down, select ‘Rooms’, and then click ‘Okay’.
Step 5: Configure Schedule Fields:
- Customise the fields for your room schedule based on the information you want to include.
Common fields include room number, name, area, occupancy, etc.
Step 6: Define Sorting and Grouping (Optional):
- If needed, set up sorting and grouping options to organise the schedule according to your preferences.
Step 7: Preview and Adjust:
- Preview the schedule to see how it looks.
- Make any necessary adjustments to the fields, sorting, or grouping.
Step 8: Save and Close:
- Save your schedule configuration.
- Close the ‘New Schedule’ dialog.
Step 9: Review and Modify:
- Once the schedule is created, review it within your project.
- If modifications are required, right-click on the schedule in the Project Browser and select ‘Edit Schedule.’
Step 10: Finalise and Document:
After ensuring that the schedule accurately reflects your project’s room information, you can use it for documentation or further analysis.
Remember, creating a room schedule in Revit allows you to efficiently manage and document information about the rooms in your project, enhancing the overall organisation and clarity of your design. If you have any specific preferences or requirements, feel free to adjust the schedule fields accordingly during the setup process.
If you want to learn more Revit tips and tricks, then check out our blog on creating rooms in Revit or if you’re looking to deepen your knowledge even further, then check out our Revit course page for in-depth learning opportunities.
Video Tutorial
Video Tutorial Transcript
From Iman, our trainer.
In this tip-of-the-week, we will look at the schedule in rooms.
First, we will change the names of the rooms. To do this, you need to click on the room you want to rename, go to the left panel named ‘Properties’ that comes up and where it says ‘Name’, you can put whatever you want to call it (like living room, dining room or kitchen).
If you have an area labelled as one room, but you do not want it to be one room, like a reception area with a staircase, you will use a room separator. To do this, go to the top panel and find ‘Room Separator’ once you have selected it, you can select the area of the room you want to exclude. After, select ‘Modify’ on the top left, and you will now see that the area you selected is no longer part of the room.
Before we create the schedule, you should save your progress. After saving your work, go to ‘Project Browser – Building 02’ at the bottom left of the page and then find ‘Schedule/Quantities (all)’. Right-click on this and select ‘New Schedule/Quantities…’. This schedule will be for rooms, so we need to ensure that we are selecting ‘Architecture’ only. Under ‘Category’, scroll down, select ‘Rooms’, and then click ‘Okay’.
We need to add the elements: select area, floor finish, level, name, number, perimeter and wall finish, and then click ‘okay’. Your schedule will now appear; however, it is not organised. ‘Floor Finish’ and ‘Wall Finish’ are not filled in, but we will cover that in next week’s tip.
Thank you for joining us!
How to Organise and Schedule in Rooms in Revit (Video Tutorial)
Video Tutorial Transcript
From Iman, our trainer.
In this tip-of-the-week, we are still talking about the schedule in rooms on Revit.
We need to reorganise the schedule, change the order of the columns, add more data and get the total areas for the rooms.
To change the order, go to ‘Properties’ on the top left and find ‘fields’, then select ‘edit’. We want ‘level’ to be listed first, so select it and then click the up arrow that says ‘push parameter up’ so it is listed first. Next, we want number, name, area, perimeter, floor finish and then wall finish, then click ’OK’. If you want to reorder based on numbers, go to sorting/grouping on the left, and from there, select sort by number. You can choose between ascending or descending, but we will keep ascending and then click ‘OK’.
If you go back to the Ground Floor diagram, you can see all the numbers are based on the order of room placement. To change it, go to ‘Properties’ and select a room. If you select reception, you can see that this is number one.
Back to the schedule, if you want to add floor finish to the rooms and make it wood, you would go to the ground floor and select a room, let’s say the office, for example. Go to room Properties, and under ‘Identity Data’, you will find floor finish; you can select the type of finish you want. There is also another way to do it
, go back to the schedule, where you can see ‘wood’ is now filled in the underfloor finish; if you want to select the floor finish from another room, click the row and select the finish from the options, now pick your floor finishings for each room.
If you look under level, you will see instead of a room name; it says ‘Not Placed’; this is because we did not place this room. But where is this room? If we look at Ground Floor Copy, you will not see it there. To remove it, go back to the Room Schedule, right-click on the row and select ‘delete’.
To see each floor finish in a separate part, we need to get the totals. This can easily be done by selecting ‘sorting/grouping’. Click ‘edit’ next to sorting/grouping; it is sorting by number. Go to ‘then by’ and select ‘Floor Finish’, next click the box for ‘Header’ and ‘Footer’ to show these, then click ‘OK’.
If you go to the Room schedule, you can see it looks messy now, which isn’t good. Go back to ‘sorting/grouping’ and deselect ‘then by’ and change ‘sort by’ to room finish. Select header and footer, and click ‘OK’. We need a total number for the area; go to ‘formatting’ on the left, select ‘Area’ in the left column and then where it says ‘No calculation,’ click this box and change it to ‘Calculate totals’ and then click ‘OK’. You can now see the total of the areas.
Thank you for joining!
Step-by-Step Guide to Creating a Room Area Schedule in Revit
Here’s a structured approach to creating a room area schedule in Revit, which aligns closely with creating a room schedule:
Open Your Revit Project:
Start by opening the Revit project where you want to create the room area schedule.
Navigate to the ‘View’ Tab:
Go to the ribbon and click on the ‘View’ tab. Under the ‘Create’ panel, select ‘Schedules’ and then choose ‘Schedule/Quantities.’
Select ‘Rooms’ Category:
In the ‘New Schedule’ dialog box, under ‘Category’, scroll down and select ‘Rooms.’ Click ‘OK’ to proceed.
Define Schedule Fields:
In the ‘Fields’ tab of the ‘Schedule Properties’ dialog box, include fields such as Room Number, Room Name, Area, Occupancy, Department, etc. Ensure ‘Area’ field is added to display room areas.
Sort and Group Rooms (Optional):
Use the ‘Sorting/Grouping’ tab to organize rooms based on parameters such as Room Number or Room Name. This helps in grouping similar rooms together for better organization.
Format Schedule Appearance:
Customise the appearance of your schedule in the ‘Formatting’ tab. Adjust settings such as text style, column widths, and header/footer options to enhance readability.
Preview and Adjust:
Preview the room area schedule to ensure it accurately displays the area information for each room. Make any necessary adjustments to fields, sorting, or formatting as needed.
Save and Place the Schedule:
Once satisfied with the schedule setup, click ‘OK’ to save the schedule. Revit will prompt you to place the schedule on a sheet view. Select the appropriate sheet and place the schedule.
Review and Modify as Needed:
Review the placed room area schedule to verify the accuracy of room area calculations. Use the ‘Edit Schedule’ option to make modifications if room areas change or updates are needed.
Document and Use for Project Management:
Use the finalized room area schedule for project documentation, space planning, and occupancy management. Update the schedule as necessary to reflect changes throughout the project lifecycle.
How do I print a room schedule in Revit?
Printing a room schedule in Revit allows you to generate a hard copy of the detailed information about rooms within your project. Follow these steps to print a room schedule effectively:
Step-by-Step Guide to Printing a Room Schedule
- Open Your Revit Project: Start by opening the Revit project containing the room schedule you want to print.
- Navigate to the ‘View’ Tab: Go to the ribbon and click on the ‘View’ tab. Under the ‘Create’ panel, select ‘Schedules’ and then choose ‘Schedule/Quantities.’
- Select the Room Schedule: In the ‘New Schedule’ dialog box, select the room schedule you want to print from the list of available schedules.
- Preview the Schedule: Click ‘OK’ to open the room schedule. Review the schedule to ensure it displays the correct information and formatting.
- Set Print Parameters: Go to the ‘File’ menu and select ‘Print Setup’ to configure print settings such as paper size, orientation, and printer selection. Adjust other settings like print margins and scaling as needed.
- Print the Schedule: Once satisfied with the print settings, click ‘Print’ to generate a hard copy of the room schedule. Revit will send the schedule to the selected printer.
- Review Printed Output: Retrieve the printed room schedule from the printer and review it to ensure all information is accurately represented. Make note of any discrepancies or formatting issues for future adjustments.
Tips for Printing Room Schedules
- Check Page Breaks: Ensure that the room schedule prints neatly across pages, especially if it’s a large schedule.
- Verify Data Accuracy: Double-check room numbers, names, areas, and other details to ensure they match the digital version of the schedule.
- Save Print Settings: Save print settings for future use to streamline printing processes for similar schedules.
How do I export a room schedule from Revit?
- Open the room schedule view.
- Choose File > Export > Reports > Schedule.
- Choose a filename and location.
- Select the required headers, delimiters and text qualifier, then export.
Revit’s schedule export produces a delimited text file that spreadsheet software can open. It does not directly create an .xlsx workbook from this command. If a schedule has been placed on a sheet, other sheet-export options may also be available.
Continue learning Revit
Review how to create and place rooms in Revit before building your schedule.